The layout and construction of the foundation shall be carried out according to the plan of the foundation to ensure that the dimensions of each relative position are accurate.
Install weighing belt conveyor, intermediate weighing bucket.
Hoisting the upper frame with a crane, connecting the upper frame with the front and rear legs with bolts, and connecting the front legs with the anchor bolts in place; Connect the oblique bearings;Then carefully check that the connection points are firm, and finally slowly remove the crane.
Install platforms, ladders, and railings
Install material hoist and cement weighing, water weighing and admixture weighing, etc.
Install the sand and stone storage bin support in place and attach the anchor bolts.
The three screw conveyors are assembled on the ground and the feed end is connected to the cement bin and the discharge end to the cement metering hopper. Connect the gas system